Commissioning Assistant
31-8
31.4.7. Check Cell Voltage Screen
Figure 163. Check Cell Voltage (Comm Asst)
Click the Check Cell Voltage button. Measure the voltage across the cell indicated, type the
value in the Measured Value field, then press <Enter>. If the measured value agrees with the
calculated value in the monitor, the Status area indicates Passed. If it fails, calibrate the
monitor to the measured value by clicking the Cal button. Note that, if there is a more
convenient cell to measure, you may change the Cell Number to any cell within the DCM.
31.4.8. Check Overall Voltage Screen
Figure 164. Check Overall Voltage (Comm Asst)
Click the Check Overall Voltage button. (Not used with BDS-40.) Measure the overall
voltage, type the value in the Measured Value field, then press <Enter>. If the measured
value agrees with the calculated value in the monitor, the Status area indicates Passed. If the
measured value fails, calibrate the monitor to the measured value by clicking the Cal button.